PROJECT MANAGEMENT:
CHAPTER 9
Project Planning
I. DEFINE PROJECT OBJECTIVE
II. DETERMINE ACTIVITIES THAT
NEED TO BE PERFORMED TO ACCOMPLISH OBJECTIVES
activity: a piece of work that consumes time
III. DEVELOP THE NETWORK PLAN
- Activity on the Arrow (AOA):
- circles represent events
- arrows are links that represent activities
- Activity in the Box (AIB):
- each activity is represented by a box
- the activity description is within the box
- each activity is linked serially by an arrow
- GANNT Chart:
- each activity is listed down the left side
- the time scale is shown along the top
|